Balance Overload Capacity (Advanced Scheduling only)
Sometimes, some work centers may be overloaded with jobs when compared to the other work centers. You must then manually schedule the jobs at the work centers to balance the load.
To view and balance overload capacity
-
Open the Interactive Load Analysis (PSINTLA) page.
- Select Planning and Scheduling> P&S Production > Scheduling > Interactive Load Analysis.
Or
-
Search for PSINTLA or Interactive Load Analysis in the Navigation box and then select Interactive Load Analysis.
The Interactive Load Analysis (PSINTLA) page appears.
-
From the Facility list, select the facility whose work center’s load you want to balance.
-
Select the work center:
-
Method 1
i. On the Toolbar, click Search .
ii. In the Work Center field, type the work center ID.
Type the starting characters of the work center to search all work centers beginning with those characters. For example, typeAS to search all work centers starting with “AS”.
iii. On the Toolbar, click Search .
iv. Select the work center from the Search For Interactive Load Analysis window.
-
Method 2
i. On the Toolbar, click Browse .
ii. Select the work center from the Browse For Interactive Load Analysis window.
-
In the Filter area, select one of the following options to choose the period you want to view:
Selection Description All Displays all periods. Overloaded Displays only overloaded periods. -
From the Calendar ID list, select the bucketing period:
-
SHIFT
-
DAILY
-
WEEKLY
-
MONTHLY
- In the Number of Days field, type the horizon.
The upper grid shows the various periods of the work center.
The overloaded periods are displayed in red.
The lower grid shows the jobs that are contributing to the overload.
-
In the upper grid, select an overloaded period.
-
In the lower grid, select the required job.