Balance Overload Capacity (Advanced Scheduling only)

Article • 6/18/2026 • 2 min read

Sometimes, some work centers may be overloaded with jobs when compared to the other work centers. You must then manually schedule the jobs at the work centers to balance the load.

To view and balance overload capacity

  1. Open the Interactive Load Analysis (PSINTLA) page.

    • Select Planning and Scheduling> P&S Production > Scheduling > Interactive Load Analysis.

    Or

    • Search for PSINTLA or Interactive Load Analysis in the Navigation box and then select Interactive Load Analysis.

      The Interactive Load Analysis (PSINTLA) page appears.

  2. From the Facility list, select the facility whose work center’s load you want to balance.

  3. Select the work center:

  1. In the Filter area, select one of the following options to choose the period you want to view:

    SelectionDescription
    AllDisplays all periods.
    OverloadedDisplays only overloaded periods.
  2. From the Calendar ID list, select the bucketing period:

  1. In the Number of Days field, type the horizon.

The upper grid shows the various periods of the work center.

The overloaded periods are displayed in red.

The lower grid shows the jobs that are contributing to the overload.

  1. In the upper grid, select an overloaded period.

  2. In the lower grid, select the required job.