Change job order information
M2M Planning and Scheduling updates the changes made to job orders in M2M ERP. If you change the job order information, you must update the schedule.
To change job order information
-
Open the Job Order page.
-
Change information about the job order:
a. In the grid, select the the Job Order number.
b. Under the Action column, click the ellipsis.
c. Select Grid Actions > Job Order.
d. In the Quantity field, specify the number of items to produce.
If you lower the quantity on a job order, you must run infinite planning or risk creating an infeasible schedule situation.
e. To re-prioritize the job order in the schedule, in the Priority field, type the new priority.
f. To freeze the start and end dates for this job order, select the Frozen check box.
g. To prevent any modifications to the job order, select the Firmed check box.
h. To sort the materials by available date, select the Available Date check box.
You can also change operational data and view materials for the job order.