Set display options for interactive planning by part
Use the Display Options window to:
-
Configure the display of supply and demand data or calculations in the Interactive Planning by Part window.
-
Set supply availability projection.
To set display options for interactive planning by part
-
Open the Interactive Planning By Part (PSINTPLP) window:
-
Click the Planning and Scheduling tab. From the P & S Production group, click Planning > Interactive Planning by Part .
-
Press Alt+T, type PSINTPLP, and press Enter.
-
-
Click Display Options.
The Display Options window appears.
-
Choose the information that appears in each column of the Demand or Supplies grids of the Interactive Planning by Part window:
a. Click the Stock tab.
b. Select the information to display:
- For each column, from the **Supply/Demand Column** list, select the information to display. - From the **PAB for Filter Condition** list, select the projected available balance (PAB) by demand type.[What do these values mean?]
-
In the Graph It area:
-
Select the appropriate check boxes to include the corresponding columns in the graphs.
-
Select the Supply check box to add a column that sums the entire quantity of parts planned for the period.
-
-
-
Click the Make tab and repeat Step 3b.
-
Close the Display Options window.