Override the vendor lead time for a part
If a part cannot be delivered within the quoted lead time, you may need to temporarily override its time fence Time fences are boundaries between different periods in the planning horizon. You can temporarily override the vendor’s lead time and designate a date for the temporary override to expire.
To override the vendor lead time for a part
-
Open the Supply/Demand by Part (PSSUPDEP) page.
- Select Planning and Scheduling > P&S Production > Planning > Supply/Demand by Part.
Or
-
Search for PSSUPDEP or Supply/Demand by Part in the Navigation box and then select Supply/Demand by Part.
The Supply/Demand by Part (PSSUPDEP) page appears.
-
Select the part:
-
Method 1
i. On the Toolbar, click Search.
ii. In the Part No field, type the part number.
Type the starting characters of the part number to search all part numbers beginning with those characters. For example, typePB to search all parts starting with “PB”.
iii. On the Toolbar, click Search.
-
Method 2
i. On the Toolbar, click Browse.
The Browse For Supply/Demand by Part window appears.
ii. Select the row that contains the required part, and click Select.
Or double-click the row that contains the required part.
-
On the Toolbar, click More Actions.
-
Select More Actions > Actions > Lead Time.
The Vendor Lead Time (PSVENDLT) window appears.
-
Click Override beside the Standard Lead Time Fence field.
The Override Lead Time Fence field appears.
-
In the Override Lead Time Fence field, specify the new date that overrides the standard lead time fence.
ClickClear to remove the Override Lead Time Fence field.
-
On the Toolbar, click Save.
-
Close the Vendor Lead Time (PSVENDLT) window.