View a schedule for the primary work center (Advanced Scheduling only) (TBD-Dev)
The primary work center is the work center associated with the routing step (as opposed to an additional resources linked to that step as well.) You view the schedule for this work center as you would view the schedule for the primary or critical capacity constrained resource. For more information about the tasks you can perform on the Gantt chart, see Related Information.
The CCR Gantt window is only available when Advanced Scheduling is active.
To view a schedule for the primary work center
-
From within M2M Planning and Scheduling:
-
Open the Advanced Scheduling menu
-
Choose CCR Gantt
-
-
Right-click the job order number in the left pane of the window and choose Job Gantt.
-
Right-click the job order number in the left pane of this chart and chose Primary Work Center Gantt.