Schedule Completions (BMGSCCMP) window

Article • 6/18/2026 • 2 min read

The Schedule Completions (BMGSCCMP) page lists all the operations of the released jobs that are scheduled for the work center, ordered by their completion time.

This window displays the following details.

FieldDescription
FacilityThe facility
Work Center NameThe work center name
Work Center IDThe work center ID
Buffer HoursThe planned buffer in hours for the work center
Current Queue HoursThe current queue in front of the work center
Last Refresh TimeThe last date/time the window was refreshed Click Refresh to refresh the screen.
Schedule Completion gridDisplays the following details: Completion time
  • The date and time at which the operation is expected to be completed Job No
  • The job number that the operation is a part of Op No
  • The operation number Part No
  • The part number Rev
  • The part revision Time to Go
  • The remaining time to go in hours Current WC
  • The work center where the job currently is. If no operation is completed, this is the work center of the first operation. Current Queue Hours
  • The WIP queue in front of the work center at the scheduled arrival time of the operation.
  • TheCurrent Queue Hours is calculated based on the scheduled completion time. Buffer Zone

  • The zone equivalent of the queue hours as compared to the Buffer target. |