Understand Material Statuses

Article • 4/27/2026 • 4 min read

The SFM Status Generation Interval calculates the material statuses based on the user-specified interval. The default interval is 15 minutes.

Shop Floor Manager windows provide information at varying levels of detail. The SFM window you are viewing may contain information in the work center, job order operation, job order, or at the component level. The material status that displays on the window is directly related to the level of detail you are viewing.

For example, a work center may show a status of Make - Short, indicating there is a shortage of one or more make items for the work center. If you drill down into that work center’s jobs, you can see which jobs are responsible for the shortage. Then further, you can drill down into the job order detail and see what components are short.

Shop Floor Manager uses the following items as a basis for determining Material Statuses:

The following chart explains the material statuses that SFM uses, and their meanings:

Source TypeStatus DescriptionIndicates ShortageDetail LevelDefinition
MakeMake - ShortXWork Center or Job OrderMake component on the JO is short
JO - StartedXMake component on the JO has a sub-job in Started status
JO - OpenXMake component on JO has a sub-job in Open status
JO - ReleasedXMake component on the JO has a sub-job in Released status
JO - Partial CompleteXMake component on the JO has a sub-job which has some operations with Qty Complete
JO - CompleteMake component on the JO has a sub-job which is Complete
BuyBuy - ShortXWork Center or Job OrderBuy item on the JO is short
PO - No POXComponent Buy item on the JO has no PO
PO - None RecvdXComponent Buy item on the JO has a PO created (Started, Open or On Hold) but no quantity received
PO - Partially RecvdComponent Buy item on the JO has a PO which has some quantity received, but not all
BlankBuy item on the JO has been received in full
StockStock - ShortXWork Center or Job OrderStock item on the JO is short
None IssuedComponent Stock item on the JO has no quantity issued to the job, but the component is not short because there is sufficient supply
None Issued - ShortXComponent Stock item on the JO has no quantity issued to the job, and has an insufficient supply
Partial IssueComponent Stock item on the JO has some quantity issued to the job and has a sufficient supply
Partial Issue -XComponent
ShortStock item on the JO has some quantity issued to the job and has an insufficient supply
BlankStock item on the JO has been issued in full
CombinationShortXWork Center or Job OrderCombination of Stock, Buy or Make shortage

  • If you select the option to Include SO Demand In Material Status in the Company Setup tab of the Setup window, you may see the status SO - Short. This status appears when the component has insufficient supply for the SO quantity.
  • If you select the option to Display Excluded Parts On BOM in the Company Setup tab of the Setup window, a message in red displays to indicate the part is excluded from displaying the material status.
  • If you did not select the Display Excluded Parts On BOM checkbox on the Company Setup Setup 2 tab of the Setup window, a message in red displays to indicate that one or more component parts are being excluded. The parts will not display on the material availability lists and will not generate material status messages.