End What-If mode

Article • 6/18/2026 • 1 min read

When you are done working in What-If mode and are ready to commit the schedule in production mode, end your What-If session.

You have two options:

To end What-If mode from within M2M Planning and Scheduling

  1. On the Menu tab select Planning and Scheduling. Click the P&S Launch group > What If .

  2. In the End Session area:

    • Click Commit to commit the changes you have made.

    • Click Roll Back to revert to the current schedule.