Check a costed bill of material
A costed bill of material details the material used to make a part and breaks down the costs for each component in the part.
You can also view the costs for a part or assembly in the item master.
- After you roll up costs in the Inventory Cost Roll Up (CRUP) page, the costs in the Costed BOMS (BOMCST) page is displayed based on the Yields in RTG.
- If the unit of measure is Each (EA) or Piece (PC), the Operation quantity will be rounded up to the next integer after the calculation with yield and used for computing the labor and overhead costs.
- If the unit of measure is other than EA or PC, the Operation quantity will remain as it is (decimal/integer) after the calculation and the same is used for computing the labor and overhead costs.
To view a costed bill of material for a part
-
Open the Costed BOMs (BOMCST) page.
-
Select Production Management > Master Data > Costed BOMs.
Or
-
Search for BOMCST in the Navigation box and then select Costed BOMs
The Costed BOMs page appears.
-
-
On the Toolbar, click Browse.
The Browse For Costed BOMs window appears.
-
Select a row and click Select. Or, double-click the item to view.
Click Cancel to exit from this window.
The costs for the part appear in the top part of the page.
Individual costs for material, labor, overhead, sub-contract/other, and total appear at the bottom of the page.
-
If the costs do not appear at the bottom of the window, click the Down Level in the child toolbar to see all the material costs for that item.
-
To view cost differences when you use another costing method, click Change Cost Method on the Toolbar.